US nuclear reactor prototype completes 2,000 hours of testing before full build

SMRTR summary

Kairos Power has completed the first testing phase of a non-nuclear reactor cavity mockup for its Hermes 2 plant in Tennessee, evaluating modular radiation shielding and remote maintenance systems. The 2,000-hour program used 3D-printed concrete forms and tested shielding plug designs, helping standardize construction methods before full commercial deployment begins.